[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896118":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896118,581,1,"单选题","某工程项目实施过程中，已完工作预算费用曲线（BCWP）与已完工作实际费用曲线（ACWP）靠得很近，而与计划工作预算费用曲线（BCWS）离得很远，则表示该工程项目在（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","A．费用与进度上均是按预定计划目标进行的",false,{"key":16,"text":17,"correct":14},"B","B．费用与进度上均没有按预定计划目标进行",{"key":19,"text":20,"correct":21},"C","费用上是按预定计划目标进行的",true,{"key":23,"text":24,"correct":14},"D","进度上是按预定计划目标进行的","按赢得值法，费用偏差CV=BCWP-ACWP;进度偏差SV＝BCWP-BCWS。若BCWP 与ACWP 靠得很近，则费用偏差很小；而BCWP 与BCWS 离得很远，则进度偏差较大，所以只是费用上是按预定计划目标进行的，故选C。其他答案不正确。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]