[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896117":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896117,581,1,"单选题","某地下工程施工合同约定，计划3 月份完成混凝土工程量500m3，合同单价为600 元\u002Fm3。该工程3 月份实际完成的混凝土工程量为400m3，实际单价700 元\u002Fm3。至3 月底，该工程的费用绩效指数（CPI）为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.800",false,{"key":16,"text":17,"correct":18},"B","0.857",true,{"key":20,"text":21,"correct":14},"C","1.167",{"key":23,"text":24,"correct":14},"D","1.250","费用绩效指数CPI=BCWP\u002FACWP＝400×600\u002F4.00×700=0.857。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]