[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896115":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896115,581,1,"单选题","某地下工程施工合同约定，计划1 月份开挖土方80000m3，合同单价均为85 元／m3。至1 月底，经确认实际开挖土方90000m3，实际单价为72 元\u002Fm3，则该工程的费用偏差（CV）为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","117",true,{"key":16,"text":17,"correct":18},"B","-117",false,{"key":20,"text":21,"correct":18},"C","85",{"key":23,"text":24,"correct":18},"D","-85","费用偏差CV=BCWP-ACWP=90000×（85-72）=117 万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]