[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896114":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896114,581,1,"单选题","某打桩工程合同约定，第一个月计划完成工程桩120 根；单价为1.2 万元／根。时值月底，经确认的承包商实际完成的工程桩为110 根；实际单价为1.3 万元／根。在第一个月度内，该打桩工程的已完工作预算费用（BCWP）为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","132",true,{"key":16,"text":17,"correct":18},"B","143",false,{"key":20,"text":21,"correct":18},"C","144",{"key":23,"text":24,"correct":18},"D","156","BCWP 是赢得值法中的参数之一，它是按已完工作量乘以预算价格而得，故为110×1.2=132 万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]