[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},896113,581,1,"单选题","某建筑工程施工至某月月末，出现了工程的费用偏差小于0、进度偏差大于0 的状况，则该工程的已完工作实际费用（ACWP）、计划工作预算费用（BCWS）和已完工作预算费用（BCWP）的关系可表示为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","BCWP>ACWP>BCWS",false,{"key":16,"text":17,"correct":14},"B","BCWS>BCWP>ACWP",{"key":19,"text":20,"correct":21},"C","ACWP>BCWP>BCWS",true,{"key":23,"text":24,"correct":14},"D","BCWS>ACWP>BCWP","按赢得值法，费用偏差CV=BCWP-ACWP；进度偏差SV=BCWP-BCWS。若CV 小于0，则ACWP 大于BCWP;SV大于0，则BCWP 大于BCWS。故有ACWP>BCWP>BCWS。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]