[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896112":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896112,581,1,"单选题","施工项目经理部在对施工机械使用费支出的控制过程中，采取合理受安排施工生产、加强机械调度工作等的成本控制措施，主要作用是控制机械的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","台班单价",false,{"key":16,"text":17,"correct":18},"B","台班数量",true,{"key":20,"text":21,"correct":14},"C","台班保养费",{"key":23,"text":24,"correct":14},"D","台班质量","施工生产的合理安排、加强机械调度等工作主要涉及台班数量，与机械台班单价、台班保养费和台班质量无直接关系，所以选B。选项A、C、D 均不合适。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]