[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896111":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896111,581,1,"单选题","施工成本的过程控制中，对于人工费和材料费都可以采用的控制方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","量价分离",true,{"key":16,"text":17,"correct":18},"B","包干控制",false,{"key":20,"text":21,"correct":18},"C","预算控制",{"key":23,"text":24,"correct":18},"D","跟踪检查","本题考查的是施工成本的过程控制方法。人工费的控制实行“量价分离”的方法；材料费控制同样按照“量价分离”原则，控制材料用量和材料价格。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]