[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896110":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},896110,581,1,"单选题","施工成本控制的步骤是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","．比较--分析--预测--纠偏--检查",true,{"key":16,"text":17,"correct":18},"B","预测--检查--比较--分析--纠偏",false,{"key":20,"text":21,"correct":18},"C","检查--比较--分析--预测--纠偏",{"key":23,"text":24,"correct":18},"D","分析--检查--比较--预测--纠偏","工成本控制的步骤如下：比较、分析、预测、纠偏、检查。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]