[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896109":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896109,581,1,"单选题","关于利用时间一成本累积曲线编制施工成本计划的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","A．所有工作都按最迟开始时间，对节约资金不利",false,{"key":16,"text":17,"correct":14},"B","B．所有工作都按最早开始时间，对节约资金有利",{"key":19,"text":20,"correct":14},"C","项目经理通过调整关键工作的最早开始时间，将成本控制在计划范围之内",{"key":22,"text":23,"correct":24},"D","所有工作都按最迟开始时间，降低了项目按期竣工的保证率",true,"本题考查的是按工程进度编制施工成本计划的方法。一般而言，所有工作都按最迟开始时间开始， 对节约资金贷款利息是有利的，但同时，也降低了项目按期竣工的保证率。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]