[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896108":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},896108,581,1,"单选题","关于竞争性成本计划、指导性成本计划和实施性成本计划三者区别的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","A．指导性成本计划是项目施工准备阶段的施工预算成本计划，比较详细",false,{"key":16,"text":17,"correct":14},"B","B．实施性成本计划是选派项目经理阶段的预算成本计划",{"key":19,"text":20,"correct":14},"C","指导性成本计划是以项目实施方案为依据编制的",{"key":22,"text":23,"correct":24},"D","竞争性成本计划是项目投标和签订合同阶段的估算成本计划，比较粗略",true,"A 中应为实施性；B 中应为指导性；C 中应为合同标书为依据。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]