[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896107":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896107,581,1,"单选题","通过加强施工定额管理和施工任务单管理，控制活劳动和物化劳动的消耗。这属于施工成本管理措施的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","技术措施",false,{"key":16,"text":17,"correct":18},"B","组织措施",true,{"key":20,"text":21,"correct":14},"C","经济措施",{"key":23,"text":24,"correct":14},"D","合同措施","本题考查的是施工成本管理的任务与措施。组织措施是从施工成本管理的组织方面采取的措施。加强施工定额管理和施工任务单管理，控制活劳动和物化劳动的损耗，加强施工调度，避免因施工计划不周和盲目调度造成窝工损失、机械利用率降低、物料积压等而使施工成本增加。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]