[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-896106":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},896106,581,1,"单选题","关于施工形象进度、产值统计、实际成本三者关系的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A．施工形象进度与产值统计所依据的工程量是相同的，但与实际成本计算依据的工程量不同",false,{"key":16,"text":17,"correct":18},"B","B．施工形象进度、产值统计、实际成本所依据的工程量应是相同的数值",true,{"key":20,"text":21,"correct":14},"C","施工形象进度、产值统计、实际成本所依据的工程量都是互不相同的",{"key":23,"text":24,"correct":14},"D","产值统计与实际成本所依据的工程量是相同的，但不同于形象进度计算所依据的工作量","本题考查的是施工成本管理的任务。形象进度、产值统计、实际成本归集三同步，即三者的取值范围应是一致的。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]