[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895989":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895989,581,1,"单选题","编制人工定额时，应计入定额时间的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","擅自离开工作岗位的时间",false,{"key":16,"text":17,"correct":18},"B","辅助工作消耗的时间",true,{"key":20,"text":21,"correct":14},"C","工作时间内聊天的时间",{"key":23,"text":24,"correct":14},"D","工作面未准备好导致的停工时间","本题考查的是人工定额的编制。施工作业的定额时间，是在拟定基本工作时间、辅助工作时间、准备与结束时间、不可避免的中断时间，以及休息时间的基础上编制的。参见教材P74。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]