[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895987":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895987,581,1,"单选题","编制人工定额时，工人必须消耗的时间不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","有效工作时间",false,{"key":16,"text":17,"correct":14},"B","休息时间",{"key":19,"text":20,"correct":14},"C","不可避免中断时间",{"key":22,"text":23,"correct":24},"D","偶然工作时间",true,"本题考查的是人工定额。必须消耗的时间包括有效工作时间、休息时间和不可避免中断时间。其中有效工作时间又包括基本工作时间、准备与结束工作时间以及辅助工作时间。@jin",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]