[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895986":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895986,581,1,"单选题","编制某施工机械台班使用定额，测定该机械小时的生产率为6 机械利用系数平均为80%，工作班延续时间为8 小时，则该机械的台班产量定额为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","64",false,{"key":16,"text":17,"correct":14},"B","60",{"key":19,"text":20,"correct":14},"C","48",{"key":22,"text":23,"correct":24},"D","38.4",true,"本题考查的是施工机械台班使用定额的编制。施工机械台班产量定额=机械生产率×工作班延续时间×机械利用系数=6×8×80%=38.4",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]