[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895984":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895984,581,1,"单选题","编制施工机械台班使用定额时，可计入定额时间的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A．因技术人员过错造成机械降低负荷情况下的工作时间",false,{"key":16,"text":17,"correct":18},"B","B．机械使用过程中进行的必要的保养所造成的中断时间",true,{"key":20,"text":21,"correct":14},"C","操作机械的工人违反劳动纪律所消耗的时间",{"key":23,"text":24,"correct":14},"D","施工组织不当造成的机械停工时间","不可避免的中断工作时间，是与工艺过程的特点、机械的使用和保养、工人休息有关的中断时间， 是必须消耗的时间。ACD 均为损失时间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]