[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895724":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895724,581,1,"单选题","( )反映建设项目建成后新增固定资产、流动资产、无形资产和其他资产价值的情况和价值，作为财产交接、检查投资计划完成情况和分析投资效果的依据。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基本建设项目概况表",false,{"key":16,"text":17,"correct":14},"B","基本建设项目竣工财务决算表",{"key":19,"text":20,"correct":21},"C","基本建设项目交付使用资产总表",true,{"key":23,"text":24,"correct":14},"D","建设项目交付使用资产明细表","(3)基本建设项目交付使用资产总表（见表6.2.3)。该表反映建项目建成后新增固定资产、流动资产、无形资产价值的情况和价值，作为财产交接、检查投资计划完成情况和分析投资效果的据。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]