[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895713":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895713,581,1,"单选题","建设周期长、建设内容多的项目，单项工程竣工，具备交付使用条件的，可编制()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单项工程竣工财务决算",true,{"key":16,"text":17,"correct":18},"B","单项工程竣工财务决算书",false,{"key":20,"text":21,"correct":18},"C","单项工程竣工财务决算报表",{"key":23,"text":24,"correct":18},"D","单项工程竣工图","项目竣工时，应编制建设项目竣工财务决算。建设周期长、建设内容多的项目，单项工程竣工，具备交付使用条件的，可编制单项工程竣工财务决算。建设项目全部竣工后应编制竣工财务总决算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]