[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895706":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895706,581,1,"单选题","完整的竣工决算所包含的内容是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工财务决算说明书、竣工财务决算报表、工程竣工图、工程竣工造价对比分析",true,{"key":16,"text":17,"correct":18},"B","竣工财务决算报表、竣工决算、工程竣工图、工程竣工造价对比分析",false,{"key":20,"text":21,"correct":18},"C","竣工财务决算说明书、竣工决算、竣工验收报告、工程竣工造价对比分析",{"key":23,"text":24,"correct":18},"D","竣工财务决算报表、工程竣工图、工程竣工造价对比分析","竣工决算主要包括竣工决算报告说明书、竣工财务决算报表、工程竣工图和工程造价比较分析四部分。竣工财务决算说明书和竣工财务决算报表两部分又称为建设项目竣工财务决算，是其核心内容。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]