[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895703":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895703,581,1,"单选题","根据《建设工程价款结算暂行办法》，在具备施工条件的前提下，发包人支付预付款的期限应是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不迟于约定的开工日期前的7 天内",true,{"key":16,"text":17,"correct":18},"B","不迟于约定的开工日期后的7 天内",false,{"key":20,"text":21,"correct":18},"C","不迟于约定的开工日期前的14 天内",{"key":23,"text":24,"correct":18},"D","不迟于约定的开工日期后的14 天内","根据《建设工程价款结算暂行办法》的规定，在具备施工条件的前提下，发包人应在双方签订合同后的一个月内或不迟于约定的开工日期前的7 天内预付工程款。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]