[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895702":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895702,581,1,"单选题","关于竣工结算的编制与审查的说法中，错误的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单位工程竣工结算由承包人编制",false,{"key":16,"text":17,"correct":14},"B","建设项目竣工总结算经发、承包人签字盖章后有效。",{"key":19,"text":20,"correct":14},"C","竣工结算的编制依据包括经批准的开、竣工报告或停、复工报告",{"key":22,"text":23,"correct":24},"D","结算中的暂列金额应减去工程价款调整与索赔、现场签证金额，若有余款归承包人",true,"结算中的暂列金额应减去工程价款调整与索赔、现场签证金额，若有余额归发包人。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]