[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895701":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895701,581,1,"单选题","根据《建设工程价款结算暂行办法》，发包人应在一定时间内预付工程款，否则，承包人应在预付时间到期后的一定时间内发出要求预付工程款的通知，若发包人仍不预付，则承包人可在发出通知的（）天后停止施工。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","14",true,{"key":23,"text":24,"correct":14},"D","28","根据《建设工程价款结算暂行办法》规定，在具备施工条件的前提下，发包人应在双方签订合同后的一个月或不迟于约定的开工日期前7 天预付工程款，否则，承包人应在预付时间到期后的10 天内向发包人发出要求预付工程款的通知，若发包人仍不预付，则承包人可在发出通知的14 天后停止施工。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]