[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895697":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895697,581,1,"单选题","关于建筑安装工程结算的编制，下列说法中正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","采用固定总价合同 的，暂列金额不得调整",false,{"key":16,"text":17,"correct":14},"B","采用固定总价合同的，税率可不按政府部门新公布的税率调整",{"key":19,"text":20,"correct":14},"C","规费应按县级建设主管部门规定的费率计算",{"key":22,"text":23,"correct":24},"D","现场签证费用应依据发承包双方签证资料确认的金额计算",true,"在工程竣工结算时，其他项目应按下列规定计价：⑴计日工应按发包人实际签证确认的事项计算。⑵暂估价应按发承包双方按照《建设工程工程量清单计价规范》的相关规定计算。⑶总承包服务费应依据合同约定金额计算，如发生调整的，以发承包双方确认调整的金额计算。⑷施工索赔费用应依据发承包双方确认的索赔事项和金额计算。⑸现场签证费用应依据发承包双方签证资料确认的金额计算。⑹暂列金额应减去工程价款调整（包括索赔、现场签证）金额计算，如有余额归发包人。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]