[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895693":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895693,581,1,"单选题","工程竣工结算的计价原则中，下列有关其他项目计价规定描述错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计日工应按发包人合同确认的事项计算",true,{"key":16,"text":17,"correct":18},"B","暂估价应按发承包双方按照《建设工程工程量清单计价规范》的相关规定计算",false,{"key":20,"text":21,"correct":18},"C","施工索赔费用应依据发承包双方确认的索赔事项和金额计算",{"key":23,"text":24,"correct":18},"D","现场签证费用应依据发承包双方签证资料确认的金额计算","本题考查的是竣工结算。其他项目应按下列规定计价： 1)计日工应按发包人实际签证确认的事项计算； 2)暂估价应按发、承包双方按照《建设工程工程量清单计价规范》GB50500—2013的相关规定计算； 3)总承包服务费应依据合同约定金额计算，如发生调整的，以发承包双方确认调整的金额计算； 4)施工索赔费用应依据发承包双方确认的索赔事项和金额计算； 5)现场签证费用应依据发承包双方签证资料确认的金额计算； 6)暂列金额应减去工程价款调整（包括索赔、现场签证）金额计算，如有余额归发包人。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]