[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895687":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895687,581,1,"单选题","国际工程中，当承包商提交书面结清单后的一定期限内，由工程师向业主发出的证书是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","期中支付证书",false,{"key":16,"text":17,"correct":18},"B","最终支付证书",true,{"key":20,"text":21,"correct":14},"C","履约证书",{"key":23,"text":24,"correct":14},"D","工程接收证书","在收到最终报表及书面结清单后28 天内，工程师应向业主发出一份最终支付证书。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]