[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895685":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895685,581,1,"单选题","根据《建设项目工程总承包合同示范文本GF-2011-0216》，下列说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预付款支付的时间和额度在通用条款中约定",false,{"key":16,"text":17,"correct":14},"B","预付款抵扣完后，承包人应及时向发包人退还预付款保函",{"key":19,"text":20,"correct":14},"C","发包人延误付款20 天以上经催告仍不付款的，承包人即可停工",{"key":22,"text":23,"correct":24},"D","合同解除发包人有权要求承包人支付尚未扣完的预付款",true,"预付款支付的时间和额度在专用条款中约定。预付款抵扣完后，发包人应及时向承包人退还预付款保函。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]