[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895683":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895683,581,1,"单选题","根据《建设项目工程总承包合同示范文本》（GF-2011-0126），发包人按付款 计划表付款时，如承包人的实际进度比约定的目标进度落后30日及以上，发包人有权 ( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","停止当期结算",false,{"key":16,"text":17,"correct":14},"B","自行调整付款计划表",{"key":19,"text":20,"correct":21},"C","与承包人商定减少当期付款额",true,{"key":23,"text":24,"correct":14},"D","与承包人协商抵减合同总额","发包人按付款计划表付款时，承包人的实际工作和（或）实际进度比付款 计划表约定的关键路径的目标任务落后30日及以上时，发包人有权与承包人商定减少 当期付款金额，并有权与承包人共同调整付款计划表。承包人以后各期的付款申请及发 包人的付款，以调整后的付款计划表为依据。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]