[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895682,581,1,"单选题","物价波动引起的价款调整，在承包商未能在竣工时间内完成工程的，应选择下列哪个指数或价格进行价格调整()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程竣工时间期满前第49天当天适用的每项指数或价格",false,{"key":16,"text":17,"correct":14},"B","现行指数或价格",{"key":19,"text":20,"correct":21},"C","以上两种指数或价格中对业主有利的指数或价格进行价格调整",true,{"key":23,"text":24,"correct":14},"D","以上两种指数或价格中对承包商有利的指数或价格进行价格调整","如果承包商未能在竣工时间内完成工程，则应选择适用下列两种指数或价格中对业主有利的指数或价格进行价格调整：(1)工程竣工时间期满前第49天当天适用的每项指数或价格；(2)现行指数或价格。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]