[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895675,581,1,"单选题","发包人发出赶工指令，若因承包人原因造成实际进度明显落后于发包人批准的项目进度计划时，以下说法正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人应采取措施，赶上项目进度计划，费用由双方协商支付",false,{"key":16,"text":17,"correct":18},"B","承包人应自费采取措施，赶上项目进度计划",true,{"key":20,"text":21,"correct":14},"C","竣工日期延误时，承包人无须承担误期赔偿",{"key":23,"text":24,"correct":14},"D","竣工日期延误时，承包人可请求发包人顺延工期，发包人应予批准","因承包人原因造成实际进度明显落后于发包人批准的项目进度计划时，承包人应自费采取措施，赶上项目进度计划；竣工日期延误时，承包人承担误期赔偿。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]