[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895663":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895663,581,1,"单选题","根据最高人民法院有关司法解释，下列不予支持的诉讼请求是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","垫资工程款利息没有约定的情况下，承包人请求支付利息",true,{"key":16,"text":17,"correct":18},"B","施工合同无效，但工程竣工验收合格，承包人请求合同约定支付工程价款",false,{"key":20,"text":21,"correct":18},"C","施工合同无效，已宪工程质量合格，承包人请求合同约定支付工程价款",{"key":23,"text":24,"correct":18},"D","施工合同无效，已完工程质量不合格但修复后工程验收合格，发包人请求承包人承担修复费用","当事人对垫资利息没有约定，承包人请求支付利息的，不予支持。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]