[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895656":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895656,581,1,"单选题","某工程合同总价为5000 万元，合同工期180 天，材料费占合同总价的60%，材料储备定额天数为25 天。材料供应在途天数为5 天。用公式计算法来求得该工程的预付款为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","417",true,{"key":16,"text":17,"correct":18},"B","500",false,{"key":20,"text":21,"correct":18},"C","694",{"key":23,"text":24,"correct":18},"D","833","本题考查预付款计算。工程预付款=年度工程总价×材料比例\u002F年度施工天数×材料储备定额天数=5000×0.6\u002F180×25=416.66 万元。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]