[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895651,581,1,"单选题","根据《建设工程工程量清单计价规范》GB 50500-2013，关于工程计量，下列说法中正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同文件中规定的各种费用支付项目应予计量",true,{"key":16,"text":17,"correct":18},"B","因异常恶劣天气造成的返工工程量不予计量",false,{"key":20,"text":21,"correct":18},"C","成本加酬金合同应按照总价合同的计量规定进行计量",{"key":23,"text":24,"correct":18},"D","总价合同应按实际完成的工程量计算","(1)工程计量的范围。工程计量的范围包括：工程量清单及工程变更所修订的工程量清单的内容；合同文件中规定的各种费用支付项目，如费用索赔、各种预付款、价格调整、违约金等",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]