[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895646,581,1,"单选题","承包人可根据确定的工程计量结果向发包人提出支付工程进度款申请，发包人应在14天内支付最高限额为()的工程价款作为工程进度款，",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","70%",false,{"key":16,"text":17,"correct":14},"B","80%",{"key":19,"text":20,"correct":21},"C","90%",true,{"key":23,"text":24,"correct":14},"D","100%","本题考查的是预付款及期中支付。进度款的支付比例按照合同约定，按期中结算价款总额计，不低于60%， 不高于90%。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]