[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895645":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895645,581,1,"单选题","国际工程中的预付款扣回，一般为工程进度累计金额超过合同价格的()时开始起扣，每月从进度款中按一定比例扣回。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5%-10%",false,{"key":16,"text":17,"correct":18},"B","10%-20%",true,{"key":20,"text":21,"correct":14},"C","10%-30%",{"key":23,"text":24,"correct":14},"D","30%-40%","本题考查的是预付款及期中支付。 国际工程中的扣款方法一般为：当工程进度款累计金额超过合同价格的10%~20%时开始起扣，每月从进度款中按一定比例扣回。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]