[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895644":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895644,581,1,"单选题","建设工程已实际交付，但施工合同没有约定付款时间，则拖欠工程款利息的起算日期为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","提交竣工结算文件之日",false,{"key":16,"text":17,"correct":14},"B","确认竣工结算文件之日",{"key":19,"text":20,"correct":14},"C","竣工验收合格之日",{"key":22,"text":23,"correct":24},"D","工程实际交付之日",true,"2) 计息日。利息从应付工程价款之日计付。当事人对付款时间没有约定或者约定不明的，下列时间视为应付款时间： ①建设工程已 实际交付的，为交付之日； ②建 设工程没有交付的，为提交竣工结算文件之曰； ③建 设工程未交付，工程价款也未结算的，为当事人起诉之日。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]