[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895637":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895637,581,1,"单选题","某进度款支付申请报告包含了下列内容：①累计已完成的合同价款；②累计已实际支付的合同价款；③本周期已完成的计日工价款；④本周期应扣回预付款。据此，发包人本周期应支付的合同价款是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①+②-③-④",false,{"key":16,"text":17,"correct":18},"B","①-②+③-④",true,{"key":20,"text":21,"correct":14},"C","②-①+③-④",{"key":23,"text":24,"correct":14},"D","①+②+③-④","进度款支付申请应包括下列内容：(1)累计已完成的合同价款。(2)累计已实际支付的合同价款。(3)本周期合计完成的合同价款：1）本周期已完成单价项目的金额；2）本周期应支付的总价项目的金额；3）本周期已完成的计日工价款；4）本周期应支付的安全文明施工费；5）本周期应增加的金额。(4)本周期合计应扣减的金额： 1)本周期应扣减的预付款；2）本周期应扣减的金额。(5)本周期实际应支付的合同价款。 发包人本期应支付的工程价款=本周期合计完成的合同价款+本期以前累计尚未支付的价款-本周期合计应扣减的金额 本期以前累计尚未支付的价款＝累计已完成的工程价款-累计已支付的工程价款",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]