[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895634,581,1,"单选题","根据《建设工程工程量清单计价规范》GB50500-2013，关于工程预付款的支付和扣回，下列说法中正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","预付款的比例原则上不低于合同金额的10%，不高于合同金额的20%",false,{"key":16,"text":17,"correct":14},"B","从已施工工程的主要材料及构件的价值相当于工程预付款数额时起扣",{"key":19,"text":20,"correct":21},"C","原已支付预付款的扣回，抵扣方式应当由双方当事人在合同中明确约定",true,{"key":23,"text":24,"correct":14},"D","发包人应在预付款扣完后14天内一次性将全额预付款保函退还给承包人","本题考查的是预付款及期中支付。选项A错误，包工包料工程的预付款的比例原则上不得低于签约合同价（扣除暂列金额）的10%，不宜高于签约合同价（扣除暂列金额）的30%(选项A是20%，所以不正确)； 选项B错误，从未施工工程尚需的主要材料及构件的价值相当于工程预付款数额时起扣。选项D错误，预付款一般逐月从工程预付款中扣除，预付款担保的担保金额也相应逐月减少。C：抵扣方式应当由双方当事人在合同中明确约定。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]