[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895631,581,1,"单选题","关于施工合同工程价款的期中支付，下列说法中正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","期中进度款的支付比例，一般不低于期中价款总额的60%",true,{"key":16,"text":17,"correct":18},"B","期中进度款的支付比例，一般不高于期中价款总额的80%",false,{"key":20,"text":21,"correct":18},"C","综合单价发生调整的项目，其增减费在竣工结算时一并结算",{"key":23,"text":24,"correct":18},"D","发承包双方如对部分计量结果存在争议，等待争议解决后再支付全部进度款","(3)进度款的支付比例。进度款的支付比例按照合同约定，按期中结算价款总额计，不低于60%，不高于90%。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]