[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895627":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895627,581,1,"单选题","关于合同履行过程中因不可抗力解除合同的价款结算与支付的说法，不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由于不可抗力解除合同的，承包人应自行支付撤离现场所需的费用",true,{"key":16,"text":17,"correct":18},"B","发包人应向承包人支付已实施或部分实施的措施项目应付价款",false,{"key":20,"text":21,"correct":18},"C","发包人一经支付材料和工程设备货款，则该材料和工程设备成为发包人的财产",{"key":23,"text":24,"correct":18},"D","发包人应向承包人支付承包人为完成合同工程而预期开支的任何合理费用","本题考查的是竣工结算。由于不可抗力解除合同的，发包人除应向承包人支付合同解除之日前已完成工程但尚未支付的合同价款，还应支付下列金额：(1) 合同中约定应由发包人承担的费用。(2) 已实施或部分实施的措施项目应付价款。(3) 承包人为合同工程合理订购且已 交付的材料和工程设备货款。发包人一经支付此项货款，该材料和工程设备即成为发包人的财产。(4)承包人撤离现场所需的合理费用，包括员工遣送费和临时工程拆除、施工设备运离现场的费用。(5)承包人为完成合同工程而预期开支的任何合理费用，且该项费用未包括在本款其他各项支付之内。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]