[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},895622,581,1,"单选题","建设工程最终结清的工作事项和时间节点包括：①提交最终结清申请单；②签发最终结清支付证书；③签发缺陷责任期终止证书；④最终结清付款；⑤缺陷责任期终止。按时间先后顺序排列正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","⑤③①②④",true,{"key":16,"text":17,"correct":18},"B","①②④⑤③",false,{"key":20,"text":21,"correct":18},"C","③①②④⑤",{"key":23,"text":24,"correct":18},"D","①③②⑤④","本题考查的是最终结清。所谓最终结清，是指合同约定的缺陷责任期终止后，承包人已按合同规定完成全部剩余工作且质量合格的，发包人与承包人结清全部剩余款项的活动。最终结清顺序：最终结清申请单、最终支付证书、最终结清付款。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]