[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895618":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895618,581,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500——2013），发包人应在工程开工后的28天内预付不低于当年施工进度计划的安全文明施工费总额的（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","30%",false,{"key":16,"text":17,"correct":14},"B","40%",{"key":19,"text":20,"correct":14},"C","50%",{"key":22,"text":23,"correct":24},"D","60%",true,"发包人应在工程开工后的28天内预付不低于当年施工进度计划的安全文明施工费总额的60%，其余部分按照提前安排的原则进行分解，与进度款同期支付。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]