[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895615":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895615,581,1,"单选题","关于施工合同履行期间的期中支付，下列说法中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","双方对工程计量结果的争议，不影响发包人对已完工工程的期中支付",false,{"key":16,"text":17,"correct":14},"B","对已签发支付证书中的计算错误，发包人不得再予修正",{"key":19,"text":20,"correct":21},"C","进度款支付申请中应包括累计已完成的合同价款",true,{"key":23,"text":24,"correct":14},"D","本周期实际支付的合同额为本期完成的合同价款合计","进度款支付申请的内容包括：(1)累计已完成的合同价款；(2)累计已实际支付的合同价款；(3)本周期合计完成的合同价款；(4)本周期合计应扣减的金额；(5)本周期实际应支付的合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]