[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895611,581,1,"单选题","某工程承包人向发包人递交了200万元的进度款支付申请。按照《建设工程工程量清单计价规范》GB50500-2013的规定，下列关于进度款支付的说法中，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","向承包人支付不少于180万元的进度款",false,{"key":16,"text":17,"correct":18},"B","向承包人支付不少于120万元的进度款",true,{"key":20,"text":21,"correct":14},"C","向承包人支付不少于200万元的进度款",{"key":23,"text":24,"correct":14},"D","向承包人支付不少于100万元的进度款","进度款支付比例，按照合同约定，按期中结算价款总额计，向承包人支付不低于60％，不高于90％的进度款。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]