[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895610,581,1,"单选题","发包人应当开始支付不低于当年施工进度计划的安全文明施工费总额60％的期限是工程开工后的()天内。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":14},"C","21",{"key":22,"text":23,"correct":24},"D","28",true,"发包人应在工程开工后的28天内预付不低于当年施工进度计划的安全文明施工费总额的60％，其余部分按照提前安排的原则进行分解，与进度款同期支付。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]