[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895608":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895608,581,1,"单选题","在用起扣点计算法扣回预付款时，起扣点计算公式为T=P-(M\u002FN)则式中N是指()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程预付款总额",false,{"key":16,"text":17,"correct":14},"B","工程合同总额",{"key":19,"text":20,"correct":21},"C","主要材料及构件所占比重",true,{"key":23,"text":24,"correct":14},"D","累计完成工程金额","起扣点的计算公式如下： T=P-(M\u002FN) 式中：T—起扣点（即工程预付款开始扣回时）的累计完成工程金额； P—承包工程合同总额。 M—工程预付款总额； N—主要材料及构件所占比重；",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]