[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895600":3},{"question":4,"library":24},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":15,"analysis":23},895600,581,1,"单选题","根据《标准施工招标文件》中的通用条款，承包人按合同约定提交的最终结清申请单中，只限于提出（ ）。 A.在合同工程接收证书颁发前 B.在合同工作接收证书颁发后 C.在竣工付款证书接收前 D.在缺陷责任期终止证书颁发后",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":13},"C",{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","承包人按合同约定提交的最终结清申请单中，只限于提出工程接收证书颁发后发生的索赔。提出索赔的期限自接受最终结清证书时终止。",{"id":6,"name":25,"category":26,"favorite":27},"建设工程造价管理基础知识","建筑工程",0]