[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895586":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895586,581,1,"单选题","在FIDIC 合同条件下，当变更的工程量与对该项工作规定的具体费率的乘积超过了接受合同额的一定比例时，其费率或单价可以调整，该比例为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10%",false,{"key":16,"text":17,"correct":14},"B","1%",{"key":19,"text":20,"correct":14},"C","0.1%",{"key":22,"text":23,"correct":24},"D","0.01%",true,"具备以下条件时，允许对某一项工作规定的费率或单价加以调整： (1)此项工作实际测量的工程量比工程量表或其他报表中规定的工程量的变动大于10%。 (2)工程量的变更与时该项工作规定的具体费率的乘积超过了接受的合同款额的0.01%。 (3)由此工程量的变更直接造成该项工作每单位工程量费用的变动超过1%。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]