[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895583":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},895583,581,1,"单选题","根据《建设项目工程总承包合同示范文本GF-2011-0216》，下列属于施工变更的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对配套工程系统的工艺调整",false,{"key":16,"text":17,"correct":18},"B","发包人要求增加的附加试验",true,{"key":20,"text":21,"correct":14},"C","对区域内基准控制点的调整",{"key":23,"text":24,"correct":14},"D","对实施赶工指令所作的调整","总承包合同示范文本中规定的施工变更包括：①因设计变更，造成施工方法改变、设备、材料、部件和工程量的增减；②发包人要求增加的附加试验、改变试验地点；③在发包人提供的项目基础资料和现场障碍资料之外，新增加的施工障碍处理；④发包人对竣工试验经验收或视为验收合格的项目，通知重新进行竣工试验；⑤因执行基准日期之后新颁布的法律、标准、规范引起的变更；⑥上述变更所需的附加工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]