[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},895582,581,1,"单选题","根据《建设项目工程总承包合同示范为本（试行）》GF-2011-2016，下列属于施工变更的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","对区域内标准高的调整",false,{"key":16,"text":17,"correct":14},"B","对备品备件采购数量的调整",{"key":19,"text":20,"correct":21},"C","发包人对竣工检验合格的项目重新进行竣工试验",true,{"key":23,"text":24,"correct":14},"D","因发包人原因暂停工程超过45天，调减受影响的部分工程","施工变更的范围包括：1）因设计变更，造成施工方法改变、设备、材料、部件和工程量的增减；2）发包人要求增加的附加试验、改变试验地点；3）在发包人提供的项目基础资料和现场障碍资料之外，新增加的施工障碍处理；4）发包人对竣工试验经验或视为验收合格的项目，通知重新进行竣工试验；5）因执行基准日期之后新颁布的法律、标准、规范引起的变更；6）上述变更所需的附加工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]