[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-895579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},895579,581,1,"单选题","在FIDIC合同条件下，当变更的工程量与对该项工作规定的具体费率的乘积超过了接受合同额的一定比例时，其费率或单价可以调整，该比例为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","10％",false,{"key":16,"text":17,"correct":14},"B","1％",{"key":19,"text":20,"correct":14},"C","0.1％",{"key":22,"text":23,"correct":24},"D","0.01％",true,"因工程量变更可以调整合同规定费率或价格的条件包括：(1)该部分工程实际测量的工程量比工程量表或其他报表中规定的工程量的变动大于10％；(2)该项部分工程工程量的变更与相对应费率的乘积超过了中标金额的0.01％；(3)由于工程量的变更直接造成该部分工程每单位工程量费用的变动超过1％；(4)该部分工程不是合同中规定的“固定费率项目”。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程造价管理基础知识","建筑工程",0]